Hydro power plant · Sitka, AK
Green Lake
Green Lake is a 19 MW hydro power plant in Sitka City and Borough, Alaska, operated by City & Borough of Sitka - (AK). Its oldest generator still running came online in 1982. In 2025 it generated 39 GWh, about what 5,700 average Alaska homes use in a year.
Green Lake in context
Among the 28 hydro plants in Alaska in the EIA's inventory, it is the 8th largest, about 3.9% of the state's 476 MW of hydro capacity.
Sitka City and Borough has 4 power plants of 1 MW or more with 62 MW in all; Green Lake is 30% of that and the largest of 2 hydro plants there.
Its capacity factor of 24% in 2025 is lower than the 34% typical for hydro plants across the US.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Green Lake (outlined) and other plants in Sitka City and Borough, shaded. 56.986, -135.123.
Plant facts
- Operator
- City & Borough of Sitka - (AK)
- Sector
- Electric Utility
- County
- Sitka City and Borough, AK
- EIA plant ID
- 313
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 9.3 MW | 1982 | – |
| 2 | Conventional Hydroelectric | 9.3 MW | 1982 | – |
Nearby
Other plants in Sitka City and Borough
Questions
Green Lake, answered
How much power does Green Lake produce?
Green Lake has 19 MW of capacity from 2 generators. In 2025 it generated 39 GWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Green Lake power?
Its 2025 output of 39 GWh equals the yearly electricity use of about 5,700 average Alaska homes (564 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Green Lake?
Green Lake is in Sitka City and Borough, Alaska, at about 56.986°, -135.123°. It is one of 4 power plants of 1 MW or more in the county.
Who operates Green Lake?
It is operated by City & Borough of Sitka - (AK) (EIA sector: Electric Utility).
When did Green Lake open?
Its oldest generator still running came online in 1982.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Alaska home's 564 kWh a month in 2025. Methodology.