Harrington is a 1.1 GW natural gas power plant in Potter County, Texas, operated by Southwestern Public Service Co. Its oldest generator still running came online in 1976. In 2025 it generated 2.0 TWh, about what 152,000 average Texas homes use in a year.

Capacity1.1 GWNameplate, September 2026
Generated2.0 TWhIn 2025
Capacity factor21%Share of the most it could make, 2025
Generators3Oldest from 1976

Harrington in context

Among the 309 natural gas plants in Texas in the EIA's inventory, it is the 20th largest, about 1.3% of the state's 83 GW of natural gas capacity.

Potter County has 2 power plants of 1 MW or more with 1.6 GW in all; Harrington is 69% of that and the largest of 2 natural gas plants there.

Its capacity factor of 21% in 2025 is close to the 23% typical for natural gas plants across the US.

The average electricity customer in Potter County goes 6.7 hours a year without power, the 174th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,00020182019202020212022202320242025GWh 2,018
02,0004,0006,00020192021202320252,018

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Harrington (outlined) and other plants in Potter County, shaded. 35.298, -101.747.

Plant facts

Operator
Southwestern Public Service Co
Sector
Electric Utility
Grid operator
SWPP
County
Potter County, TX
EIA plant ID
6193
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Natural Gas Steam Turbine 360 MW 1976 2036
2 Natural Gas Steam Turbine 360 MW 1978 2038
3 Natural Gas Steam Turbine 360 MW 1980 2040

Nearby

Other plants in Potter County

Questions

Harrington, answered

How much power does Harrington produce?

Harrington has 1.1 GW of capacity from 3 generators. In 2025 it generated 2.0 TWh, 21% of the most it could have made running flat out all year (its capacity factor).

How many homes does Harrington power?

Its 2025 output of 2.0 TWh equals the yearly electricity use of about 152,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Harrington?

Harrington is in Potter County, Texas, at about 35.298°, -101.747°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Potter County goes 6.7 hours a year without power, the 174th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Harrington?

It is operated by Southwestern Public Service Co (EIA sector: Electric Utility), and it feeds the Southwest Power Pool.

When did Harrington open?

Its oldest generator still running came online in 1976. Planned retirements are scheduled for 2036, 2038, 2040.