Solar power plant · Alamosa, CO
Hooper Solar
Hooper Solar is a 52 MW solar power plant in Alamosa County, Colorado, operated by Solar Star Colorado III, LLC. Its oldest generator still running came online in 2015. In 2025 it generated 122 GWh, about what 15,000 average Colorado homes use in a year.
Hooper Solar in context
Among the 185 solar plants in Colorado in the EIA's inventory, it is the 16th largest, about 1.4% of the state's 3.8 GW of solar capacity.
Alamosa County has 10 power plants of 1 MW or more with 203 MW in all; Hooper Solar is 26% of that and the largest of 9 solar plants there.
Its capacity factor of 27% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Alamosa County goes 2.8 hours a year without power, the 23rd most of 39 counties in Colorado. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Hooper Solar (outlined) and other plants in Alamosa County, shaded. 37.692, -105.991.
Plant facts
- Operator
- Solar Star Colorado III, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PSCO
- County
- Alamosa County, CO
- EIA plant ID
- 60008
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SCCO3 | Solar Photovoltaic | 52 MW | 2015 | – |
Nearby
Other plants in Alamosa County
Questions
Hooper Solar, answered
How much power does Hooper Solar produce?
Hooper Solar has 52 MW of capacity from one generator. In 2025 it generated 122 GWh, 27% of the most it could have made running flat out all year (its capacity factor).
How many homes does Hooper Solar power?
Its 2025 output of 122 GWh equals the yearly electricity use of about 15,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Hooper Solar?
Hooper Solar is in Alamosa County, Colorado, at about 37.692°, -105.991°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Alamosa County goes 2.8 hours a year without power, the 23rd most of 39 counties in Colorado. The county's page has the full outage record.
Who operates Hooper Solar?
It is operated by Solar Star Colorado III, LLC (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.
When did Hooper Solar open?
Its oldest generator still running came online in 2015.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.