Natural gas power plant · McLeod, MN
Hutchinson Plant #2
Hutchinson Plant #2 is a 91 MW natural gas power plant in McLeod County, Minnesota, operated by Hutchinson Utilities Comm. Its oldest generator still running came online in 1994. In 2025 it generated 28 GWh, about what 3,200 average Minnesota homes use in a year.
Hutchinson Plant #2 in context
Among the 34 natural gas plants in Minnesota in the EIA's inventory, it is the 16th largest, about 1.4% of the state's 6.4 GW of natural gas capacity.
McLeod County has 20 power plants of 1 MW or more with 189 MW in all; Hutchinson Plant #2 is 48% of that and the largest of 2 natural gas plants there.
Its capacity factor of 4% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in McLeod County goes 0.8 hours a year without power, the 52nd most of 54 counties in Minnesota. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Hutchinson Plant #2 (outlined) and other plants in McLeod County, shaded. 44.889, -94.349.
Plant facts
- Operator
- Hutchinson Utilities Comm
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- McLeod County, MN
- EIA plant ID
- 6358
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2 | Natural Gas Fired Combined Cycle | 54 MW | 1994 | – |
| 9 | Natural Gas Fired Combustion Turbine | 25 MW | 2001 | – |
| 3 | Natural Gas Fired Combined Cycle | 12 MW | 1994 | – |
Nearby
Other plants in McLeod County
Questions
Hutchinson Plant #2, answered
How much power does Hutchinson Plant #2 produce?
Hutchinson Plant #2 has 91 MW of capacity from 3 generators. In 2025 it generated 28 GWh, 4% of the most it could have made running flat out all year (its capacity factor).
How many homes does Hutchinson Plant #2 power?
Its 2025 output of 28 GWh equals the yearly electricity use of about 3,200 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Hutchinson Plant #2?
Hutchinson Plant #2 is in McLeod County, Minnesota, at about 44.889°, -94.349°. It is one of 20 power plants of 1 MW or more in the county. The average electricity customer in McLeod County goes 0.8 hours a year without power, the 52nd most of 54 counties in Minnesota. The county's page has the full outage record.
Who operates Hutchinson Plant #2?
It is operated by Hutchinson Utilities Comm (EIA sector: Electric Utility), and it feeds MISO.
When did Hutchinson Plant #2 open?
Its oldest generator still running came online in 1994.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.