Wind power plant · Dickinson, IA
Iowa Lakes Superior Wind Farm
Iowa Lakes Superior Wind Farm is a 11 MW wind power plant in Dickinson County, Iowa, operated by Iowa Lakes Electric Coop. Its oldest generator still running came online in 2009. In 2025 it generated 35 GWh, about what 3,400 average Iowa homes use in a year.
Iowa Lakes Superior Wind Farm in context
Among the 123 wind plants in Iowa in the EIA's inventory, it is the 85th largest, about 0.1% of the state's 13 GW of wind capacity.
Dickinson County has 5 power plants of 1 MW or more with 165 MW in all; Iowa Lakes Superior Wind Farm is 6% of that and the 3rd largest of 3 wind plants there.
Its capacity factor of 38% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Dickinson County goes 2.8 hours a year without power, the 60th most of 98 counties in Iowa. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Iowa Lakes Superior Wind Farm (outlined) and other plants in Dickinson County, shaded. 43.445, -94.980.
Plant facts
- Operator
- Iowa Lakes Electric Coop
- Sector
- Electric Utility
- Grid operator
- SWPP
- County
- Dickinson County, IA
- EIA plant ID
- 57252
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SUP1 | Onshore Wind Turbine | 11 MW | 2009 | – |
Nearby
Other plants in Dickinson County
Questions
Iowa Lakes Superior Wind Farm, answered
How much power does Iowa Lakes Superior Wind Farm produce?
Iowa Lakes Superior Wind Farm has 11 MW of capacity from one generator. In 2025 it generated 35 GWh, 38% of the most it could have made running flat out all year (its capacity factor).
How many homes does Iowa Lakes Superior Wind Farm power?
Its 2025 output of 35 GWh equals the yearly electricity use of about 3,400 average Iowa homes (861 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Iowa Lakes Superior Wind Farm?
Iowa Lakes Superior Wind Farm is in Dickinson County, Iowa, at about 43.445°, -94.980°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Dickinson County goes 2.8 hours a year without power, the 60th most of 98 counties in Iowa. The county's page has the full outage record.
Who operates Iowa Lakes Superior Wind Farm?
It is operated by Iowa Lakes Electric Coop (EIA sector: Electric Utility), and it feeds the Southwest Power Pool.
When did Iowa Lakes Superior Wind Farm open?
Its oldest generator still running came online in 2009.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Iowa home's 861 kWh a month in 2025. Methodology.