Wind power plant · Ford, KS

Iron Star Wind Project

Iron Star Wind Project is a 298 MW wind power plant in Ford County, Kansas, operated by Engie North America. Its oldest generator still running came online in 2021. In 2025 it generated 1.2 TWh, about what 117,000 average Kansas homes use in a year.

Capacity298 MWNameplate, September 2026
Generated1.2 TWhIn 2025
Capacity factor47%Share of the most it could make, 2025
Generators1Oldest from 2021

Iron Star Wind Project in context

Among the 52 wind plants in Kansas in the EIA's inventory, it is the 8th largest, about 3.1% of the state's 9.7 GW of wind capacity.

Ford County has 8 power plants of 1 MW or more with 1.5 GW in all; Iron Star Wind Project is 20% of that and the largest of 6 wind plants there.

Its capacity factor of 47% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Ford County goes 3.4 hours a year without power. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,50020212022202320242025GWh 1,225
05001,0001,500202120222023202420251,225

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Iron Star Wind Project (outlined) and other plants in Ford County, shaded. 37.649, -99.981.

Plant facts

Operator
Engie North America
Sector
IPP Non-CHP
Grid operator
SWPP
County
Ford County, KS
EIA plant ID
64003
Where Kansas's power comes from → Kansas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
WTG1 Onshore Wind Turbine 298 MW 2021 –

Questions

Iron Star Wind Project, answered

How much power does Iron Star Wind Project produce?

Iron Star Wind Project has 298 MW of capacity from one generator. In 2025 it generated 1.2 TWh, 47% of the most it could have made running flat out all year (its capacity factor).

How many homes does Iron Star Wind Project power?

Its 2025 output of 1.2 TWh equals the yearly electricity use of about 117,000 average Kansas homes (876 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Iron Star Wind Project?

Iron Star Wind Project is in Ford County, Kansas, at about 37.649°, -99.981°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Ford County goes 3.4 hours a year without power. The county's page has the full outage record.

Who operates Iron Star Wind Project?

It is operated by Engie North America (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Iron Star Wind Project open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Kansas home's 876 kWh a month in 2025. Methodology.