Solar power plant · Dawson, TX
Lamesa Solar
Lamesa Solar is a 102 MW solar power plant in Dawson County, Texas, operated by Southern Power Co. Its oldest generator still running came online in 2017. In 2025 it generated 223 GWh, about what 17,000 average Texas homes use in a year.
Lamesa Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 140th largest, about 0.3% of the state's 37 GW of solar capacity.
Dawson County has 4 power plants of 1 MW or more with 464 MW in all; Lamesa Solar is 22% of that and the largest of 2 solar plants there.
Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Dawson County goes 7.8 hours a year without power, the 150th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Lamesa Solar (outlined) and other plants in Dawson County, shaded. 32.716, -101.927.
Plant facts
- Operator
- Southern Power Co
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Dawson County, TX
- EIA plant ID
- 60372
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| LSPV1 | Solar Photovoltaic | 102 MW | 2017 | – |
Nearby
Other plants in Dawson County
Questions
Lamesa Solar, answered
How much power does Lamesa Solar produce?
Lamesa Solar has 102 MW of capacity from one generator. In 2025 it generated 223 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does Lamesa Solar power?
Its 2025 output of 223 GWh equals the yearly electricity use of about 17,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Lamesa Solar?
Lamesa Solar is in Dawson County, Texas, at about 32.716°, -101.927°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Dawson County goes 7.8 hours a year without power, the 150th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Lamesa Solar?
It is operated by Southern Power Co (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Lamesa Solar open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.