Wind power plant · Zapata, TX
Las Lomas Wind Project
Las Lomas Wind Project is a 202 MW wind power plant in Zapata County, Texas, operated by Engie North America. Its oldest generator still running came online in 2020. In 2025 it generated 583 GWh, about what 44,000 average Texas homes use in a year.
Las Lomas Wind Project in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 90th largest, about 0.4% of the state's 45 GW of wind capacity.
Zapata County has 4 power plants of 1 MW or more with 441 MW in all; Las Lomas Wind Project is 46% of that and the 2nd largest of 2 wind plants there.
Its capacity factor of 33% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Zapata County goes 13 hours a year without power, the 95th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Las Lomas Wind Project (outlined) and other plants in Zapata County, shaded. 26.698, -99.057.
Plant facts
- Operator
- Engie North America
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Zapata County, TX
- EIA plant ID
- 63101
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WTG | Onshore Wind Turbine | 202 MW | 2020 | – |
Nearby
Other plants in Zapata County
Questions
Las Lomas Wind Project, answered
How much power does Las Lomas Wind Project produce?
Las Lomas Wind Project has 202 MW of capacity from one generator. In 2025 it generated 583 GWh, 33% of the most it could have made running flat out all year (its capacity factor).
How many homes does Las Lomas Wind Project power?
Its 2025 output of 583 GWh equals the yearly electricity use of about 44,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Las Lomas Wind Project?
Las Lomas Wind Project is in Zapata County, Texas, at about 26.698°, -99.057°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Zapata County goes 13 hours a year without power, the 95th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Las Lomas Wind Project?
It is operated by Engie North America (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Las Lomas Wind Project open?
Its oldest generator still running came online in 2020.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.