Wind power plant · Kossuth, IA
Ledyard Windpower, LLC
Ledyard Windpower, LLC is a 207 MW wind power plant in Kossuth County, Iowa, operated by Deriva Energy. Its oldest generator still running came online in 2022. In 2025 it generated 596 GWh, about what 58,000 average Iowa homes use in a year.
Ledyard Windpower, LLC in context
Among the 123 wind plants in Iowa in the EIA's inventory, it is the 20th largest, about 1.5% of the state's 13 GW of wind capacity.
Kossuth County has 7 power plants of 1 MW or more with 462 MW in all; Ledyard Windpower, LLC is 45% of that and the largest of 5 wind plants there.
Its capacity factor of 33% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Kossuth County goes 1.6 hours a year without power, the 89th most of 98 counties in Iowa. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Ledyard Windpower, LLC (outlined) and other plants in Kossuth County, shaded. 43.430, -94.107.
Plant facts
- Operator
- Deriva Energy
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Kossuth County, IA
- EIA plant ID
- 65390
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| LDYRD | Onshore Wind Turbine | 207 MW | 2022 | – |
Nearby
Other plants in Kossuth County
Questions
Ledyard Windpower, LLC, answered
How much power does Ledyard Windpower, LLC produce?
Ledyard Windpower, LLC has 207 MW of capacity from one generator. In 2025 it generated 596 GWh, 33% of the most it could have made running flat out all year (its capacity factor).
How many homes does Ledyard Windpower, LLC power?
Its 2025 output of 596 GWh equals the yearly electricity use of about 58,000 average Iowa homes (861 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Ledyard Windpower, LLC?
Ledyard Windpower, LLC is in Kossuth County, Iowa, at about 43.430°, -94.107°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Kossuth County goes 1.6 hours a year without power, the 89th most of 98 counties in Iowa. The county's page has the full outage record.
Who operates Ledyard Windpower, LLC?
It is operated by Deriva Energy (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Ledyard Windpower, LLC open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Iowa home's 861 kWh a month in 2025. Methodology.