Hydro power plant · Lincoln, WA

Long Lake

Long Lake is a 70 MW hydro power plant in Lincoln County, Washington, operated by Avista Corp. Its oldest generator still running came online in 1915. In 2025 it generated 435 GWh, about what 38,000 average Washington homes use in a year.

Capacity70 MWNameplate, September 2026
Generated435 GWhIn 2025
Capacity factor71%Share of the most it could make, 2025
Generators4Oldest from 1915

Long Lake in context

Among the 73 hydro plants in Washington in the EIA's inventory, it is the 28th largest, about 0.3% of the state's 22 GW of hydro capacity.

Lincoln County has 2 power plants of 1 MW or more with 113 MW in all; Long Lake is 62% of that and the largest of 2 hydro plants there.

Its capacity factor of 71% in 2025 is higher than the 34% typical for hydro plants across the US.

The average electricity customer in Lincoln County goes 9.9 hours a year without power, the 7th most of 31 counties in Washington. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060020182019202020212022202320242025GWh 435
02004006002019202120232025435

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Long Lake (outlined) and other plants in Lincoln County, shaded. 47.834, -117.836.

Plant facts

Operator
Avista Corp
Sector
Electric Utility
Grid operator
AVA
County
Lincoln County, WA
EIA plant ID
3867
Where Washington's power comes from → Washington power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Conventional Hydroelectric 18 MW 1915 –
2 Conventional Hydroelectric 18 MW 1915 –
3 Conventional Hydroelectric 18 MW 1919 –
4 Conventional Hydroelectric 18 MW 1924 –

Nearby

Other plants in Lincoln County

Questions

Long Lake, answered

How much power does Long Lake produce?

Long Lake has 70 MW of capacity from 4 generators. In 2025 it generated 435 GWh, 71% of the most it could have made running flat out all year (its capacity factor).

How many homes does Long Lake power?

Its 2025 output of 435 GWh equals the yearly electricity use of about 38,000 average Washington homes (945 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Long Lake?

Long Lake is in Lincoln County, Washington, at about 47.834°, -117.836°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Lincoln County goes 9.9 hours a year without power, the 7th most of 31 counties in Washington. The county's page has the full outage record.

Who operates Long Lake?

It is operated by Avista Corp (EIA sector: Electric Utility), and it feeds balancing authority AVA.

When did Long Lake open?

Its oldest generator still running came online in 1915.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Washington home's 945 kWh a month in 2025. Methodology.