Solar power plant · Orange, VA

Madison Solar (VA)

Madison Solar (VA) is a 63 MW solar power plant in Orange County, Virginia, operated by AES Clean Energy. Its oldest generator still running came online in 2024. In 2025 it generated 119 GWh, about what 9,300 average Virginia homes use in a year.

Capacity63 MWNameplate, September 2026
Generated119 GWhIn 2025
Capacity factor22%Share of the most it could make, 2025
Generators1Oldest from 2024

Madison Solar (VA) in context

Among the 144 solar plants in Virginia in the EIA's inventory, it is the 36th largest, about 1.2% of the state's 5.3 GW of solar capacity.

Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Orange County goes 10.0 hours a year without power, the 68th most of 123 counties in Virginia. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020242025GWh 119
05010015020242025119

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Madison Solar (VA) (outlined) and other plants in Orange County, shaded. 38.288, -77.840.

Plant facts

Operator
AES Clean Energy
Sector
IPP Non-CHP
Grid operator
PJM
County
Orange County, VA
EIA plant ID
66316
Where Virginia's power comes from → Virginia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
MDSO Solar Photovoltaic 63 MW 2024 –

Questions

Madison Solar (VA), answered

How much power does Madison Solar (VA) produce?

Madison Solar (VA) has 63 MW of capacity from one generator. In 2025 it generated 119 GWh, 22% of the most it could have made running flat out all year (its capacity factor).

How many homes does Madison Solar (VA) power?

Its 2025 output of 119 GWh equals the yearly electricity use of about 9,300 average Virginia homes (1,067 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Madison Solar (VA)?

Madison Solar (VA) is in Orange County, Virginia, at about 38.288°, -77.840°. The average electricity customer in Orange County goes 10.0 hours a year without power, the 68th most of 123 counties in Virginia. The county's page has the full outage record.

Who operates Madison Solar (VA)?

It is operated by AES Clean Energy (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Madison Solar (VA) open?

Its oldest generator still running came online in 2024.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Virginia home's 1,067 kWh a month in 2025. Methodology.