Biomass power plant · Russell, AL

Mead Coated Board

Mead Coated Board is a 121 MW biomass power plant in Russell County, Alabama, operated by Mead Coated Board Inc. Its oldest generator still running came online in 1966. In 2025 it generated 724 GWh, about what 53,000 average Alabama homes use in a year.

Capacity121 MWNameplate, September 2026
Generated724 GWhIn 2025
Capacity factor69%Share of the most it could make, 2025
Generators3Oldest from 1966

Mead Coated Board in context

Among the 14 other-fuel plants in Alabama in the EIA's inventory, it is the largest, about 17% of the state's 702 MW of other-fuel capacity.

Russell County has 2 power plants of 1 MW or more with 151 MW in all; Mead Coated Board is 80% of that.

Its capacity factor of 69% in 2025 is higher than the 25% typical for biomass plants across the US.

The average electricity customer in Russell County goes 3.8 hours a year without power, the 48th most of 60 counties in Alabama. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 724
02004006008001,0002019202120232025724

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Mead Coated Board (outlined) and other plants in Russell County, shaded. 32.176, -85.027.

Plant facts

Operator
Mead Coated Board Inc
Sector
Industrial CHP
Grid operator
SOCO
County
Russell County, AL
EIA plant ID
54802
  • Other96 MW79%
  • Natural gas25 MW21%
Where Alabama's power comes from → Alabama power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN2 Wood/Wood Waste Biomass 56 MW 1990 –
GEN1 Wood/Wood Waste Biomass 40 MW 1966 –
GEN3 Natural Gas Fired Combustion Turbine 25 MW 1998 –

Nearby

Other plants in Russell County

Questions

Mead Coated Board, answered

How much power does Mead Coated Board produce?

Mead Coated Board has 121 MW of capacity from 3 generators. In 2025 it generated 724 GWh, 69% of the most it could have made running flat out all year (its capacity factor).

How many homes does Mead Coated Board power?

Its 2025 output of 724 GWh equals the yearly electricity use of about 53,000 average Alabama homes (1,145 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Mead Coated Board?

Mead Coated Board is in Russell County, Alabama, at about 32.176°, -85.027°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Russell County goes 3.8 hours a year without power, the 48th most of 60 counties in Alabama. The county's page has the full outage record.

Who operates Mead Coated Board?

It is operated by Mead Coated Board Inc (EIA sector: Industrial CHP), and it feeds Southern Company.

When did Mead Coated Board open?

Its oldest generator still running came online in 1966.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Alabama home's 1,145 kWh a month in 2025. Methodology.