Wind power plant · Woodford, IL

Minonk Wind Farm

Minonk Wind Farm is a 200 MW wind power plant in Woodford County, Illinois, operated by Algonquin Power Co. Its oldest generator still running came online in 2012. In 2025 it generated 623 GWh, about what 72,000 average Illinois homes use in a year.

Capacity200 MWNameplate, September 2026
Generated623 GWhIn 2025
Capacity factor36%Share of the most it could make, 2025
Generators1Oldest from 2012

Minonk Wind Farm in context

Among the 56 wind plants in Illinois in the EIA's inventory, it is the 20th largest, about 2.3% of the state's 8.7 GW of wind capacity.

Woodford County has 2 power plants of 1 MW or more with 205 MW in all; Minonk Wind Farm is 98% of that.

Its capacity factor of 36% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Woodford County goes 3.1 hours a year without power, the 70th most of 101 counties in Illinois. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 623
02004006008002019202120232025623

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Minonk Wind Farm (outlined) and other plants in Woodford County, shaded. 40.889, -88.997.

Plant facts

Operator
Algonquin Power Co
Sector
IPP Non-CHP
Grid operator
PJM
County
Woodford County, IL
EIA plant ID
57284
Where Illinois's power comes from → Illinois power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 200 MW 2012 –

Nearby

Other plants in Woodford County

Cottonwood - IL · 4.9 MW

Questions

Minonk Wind Farm, answered

How much power does Minonk Wind Farm produce?

Minonk Wind Farm has 200 MW of capacity from one generator. In 2025 it generated 623 GWh, 36% of the most it could have made running flat out all year (its capacity factor).

How many homes does Minonk Wind Farm power?

Its 2025 output of 623 GWh equals the yearly electricity use of about 72,000 average Illinois homes (716 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Minonk Wind Farm?

Minonk Wind Farm is in Woodford County, Illinois, at about 40.889°, -88.997°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Woodford County goes 3.1 hours a year without power, the 70th most of 101 counties in Illinois. The county's page has the full outage record.

Who operates Minonk Wind Farm?

It is operated by Algonquin Power Co (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Minonk Wind Farm open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Illinois home's 716 kWh a month in 2025. Methodology.