Monument is a 14 MW oil power plant in Montgomery County, Ohio, operated by Kimura Power LLC. Its oldest generator still running came online in 1968. In 2025 it generated 0.5 GWh, about what 48 average Ohio homes use in a year.

Capacity14 MWNameplate, September 2026
Generated0.5 GWhIn 2025
Capacity factor0%Share of the most it could make, 2025
Generators5Oldest from 1968

Monument in context

Among the 56 other-fuel plants in Ohio in the EIA's inventory, it is the 12th largest, about 1.5% of the state's 902 MW of other-fuel capacity.

Montgomery County has 5 power plants of 1 MW or more with 855 MW in all; Monument is 2% of that.

Its capacity factor of 0% in 2025 is lower than the 25% typical for oil plants across the US.

The average electricity customer in Montgomery County goes 3.8 hours a year without power, the 61st most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0001111201820192021202220242025GWh 1
00011112018201920212022202420251

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Monument (outlined) and other plants in Montgomery County, shaded. 39.767, -84.174.

Plant facts

Operator
Kimura Power LLC
Sector
IPP Non-CHP
Grid operator
PJM
County
Montgomery County, OH
EIA plant ID
2851
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Petroleum Liquids 2.7 MW 1968 –
2 Petroleum Liquids 2.7 MW 1968 –
3 Petroleum Liquids 2.7 MW 1968 –
4 Petroleum Liquids 2.7 MW 1968 –
5 Petroleum Liquids 2.7 MW 1968 –

Nearby

Other plants in Montgomery County

Questions

Monument, answered

How much power does Monument produce?

Monument has 14 MW of capacity from 5 generators. In 2025 it generated 0.5 GWh, 0% of the most it could have made running flat out all year (its capacity factor).

How many homes does Monument power?

Its 2025 output of 0.5 GWh equals the yearly electricity use of about 48 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Monument?

Monument is in Montgomery County, Ohio, at about 39.767°, -84.174°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Montgomery County goes 3.8 hours a year without power, the 61st most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Monument?

It is operated by Kimura Power LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Monument open?

Its oldest generator still running came online in 1968.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.