Solar power plant · Livingston, NY
Morris Ridge Solar
Morris Ridge Solar is a 177 MW solar power plant in Livingston County, New York, operated by Morris Ridge Solar Energy Center, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 313 GWh, about what 45,000 average New York homes use in a year.
Morris Ridge Solar in context
Among the 730 solar plants in New York in the EIA's inventory, it is the largest, about 5.5% of the state's 3.2 GW of solar capacity.
Livingston County has 11 power plants of 1 MW or more with 222 MW in all; Morris Ridge Solar is 80% of that and the largest of 11 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Livingston County goes 3.5 hours a year without power, the 52nd most of 62 counties in New York. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Morris Ridge Solar (outlined) and other plants in Livingston County, shaded. 42.663, -77.891.
Plant facts
- Operator
- Morris Ridge Solar Energy Center, LLC
- Sector
- IPP Non-CHP
- Grid operator
- NYIS
- County
- Livingston County, NY
- EIA plant ID
- 68274
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| MOR01 | Solar Photovoltaic | 177 MW | 2024 | – |
Nearby
Other plants in Livingston County
Questions
Morris Ridge Solar, answered
How much power does Morris Ridge Solar produce?
Morris Ridge Solar has 177 MW of capacity from one generator. In 2025 it generated 313 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Morris Ridge Solar power?
Its 2025 output of 313 GWh equals the yearly electricity use of about 45,000 average New York homes (586 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Morris Ridge Solar?
Morris Ridge Solar is in Livingston County, New York, at about 42.663°, -77.891°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Livingston County goes 3.5 hours a year without power, the 52nd most of 62 counties in New York. The county's page has the full outage record.
Who operates Morris Ridge Solar?
It is operated by Morris Ridge Solar Energy Center, LLC (EIA sector: IPP Non-CHP), and it feeds the New York ISO.
When did Morris Ridge Solar open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average New York home's 586 kWh a month in 2025. Methodology.