Hydro power plant · Montrose, CO
Morrow Point
Morrow Point is a 173 MW hydro power plant in Montrose County, Colorado, operated by U S Bureau of Reclamation. Its oldest generator still running came online in 1970. In 2025 it generated 263 GWh, about what 33,000 average Colorado homes use in a year.
Morrow Point in context
Among the 47 hydro plants in Colorado in the EIA's inventory, it is the largest, about 25% of the state's 688 MW of hydro capacity.
Montrose County has 9 power plants of 1 MW or more with 228 MW in all; Morrow Point is 76% of that and the largest of 7 hydro plants there.
Its capacity factor of 17% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in Montrose County goes 1.5 hours a year without power, the 35th most of 39 counties in Colorado. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Morrow Point (outlined) and other plants in Montrose County, shaded. 38.452, -107.539.
Plant facts
- Operator
- U S Bureau of Reclamation
- Sector
- Electric Utility
- Grid operator
- WACM
- County
- Montrose County, CO
- EIA plant ID
- 514
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 87 MW | 1970 | – |
| 2 | Conventional Hydroelectric | 87 MW | 1971 | – |
Nearby
Other plants in Montrose County
Questions
Morrow Point, answered
How much power does Morrow Point produce?
Morrow Point has 173 MW of capacity from 2 generators. In 2025 it generated 263 GWh, 17% of the most it could have made running flat out all year (its capacity factor).
How many homes does Morrow Point power?
Its 2025 output of 263 GWh equals the yearly electricity use of about 33,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Morrow Point?
Morrow Point is in Montrose County, Colorado, at about 38.452°, -107.539°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Montrose County goes 1.5 hours a year without power, the 35th most of 39 counties in Colorado. The county's page has the full outage record.
Who operates Morrow Point?
It is operated by U S Bureau of Reclamation (EIA sector: Electric Utility), and it feeds WAPA Rocky Mountain.
When did Morrow Point open?
Its oldest generator still running came online in 1970.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.