Nestlewood Solar is a 80 MW solar power plant in Clermont County, Ohio, operated by Nestlewood Solar. Its oldest generator still running came online in 2023. In 2025 it generated 157 GWh, about what 15,000 average Ohio homes use in a year.
Nestlewood Solar in context
Among the 77 solar plants in Ohio in the EIA's inventory, it is the 25th largest, about 1.6% of the state's 5.0 GW of solar capacity.
Clermont County has 2 power plants of 1 MW or more with 84 MW in all; Nestlewood Solar is 95% of that.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Clermont County goes 6.9 hours a year without power, the 31st most of 88 counties in Ohio. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Nestlewood Solar (outlined) and other plants in Clermont County, shaded. 38.925, -84.017.
Plant facts
- Operator
- Nestlewood Solar
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Clermont County, OH
- EIA plant ID
- 65215
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| NSTLW | Solar Photovoltaic | 80 MW | 2023 | – |
Nearby
Other plants in Clermont County
Questions
Nestlewood Solar, answered
How much power does Nestlewood Solar produce?
Nestlewood Solar has 80 MW of capacity from one generator. In 2025 it generated 157 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Nestlewood Solar power?
Its 2025 output of 157 GWh equals the yearly electricity use of about 15,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Nestlewood Solar?
Nestlewood Solar is in Clermont County, Ohio, at about 38.925°, -84.017°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Clermont County goes 6.9 hours a year without power, the 31st most of 88 counties in Ohio. The county's page has the full outage record.
Who operates Nestlewood Solar?
It is operated by Nestlewood Solar (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Nestlewood Solar open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.