Wind power plant · Poweshiek, IA
North English
North English is a 340 MW wind power plant in Poweshiek County, Iowa, operated by MidAmerican Energy Co. Its oldest generator still running came online in 2018. In 2025 it generated 1.3 TWh, about what 128,000 average Iowa homes use in a year.
North English in context
Among the 123 wind plants in Iowa in the EIA's inventory, it is the 5th largest, about 2.5% of the state's 13 GW of wind capacity.
Poweshiek County has 8 power plants of 1 MW or more with 538 MW in all; North English is 63% of that and the largest of 3 wind plants there.
Its capacity factor of 44% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Poweshiek County goes 21 hours a year without power, the 2nd most of 98 counties in Iowa. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
North English (outlined) and other plants in Poweshiek County, shaded. 41.643, -92.499.
Plant facts
- Operator
- MidAmerican Energy Co
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Poweshiek County, IA
- EIA plant ID
- 62133
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GT1 | Onshore Wind Turbine | 200 MW | 2018 | – |
| 1 | Onshore Wind Turbine | 140 MW | 2019 | – |
Nearby
Other plants in Poweshiek County
Questions
North English, answered
How much power does North English produce?
North English has 340 MW of capacity from 2 generators. In 2025 it generated 1.3 TWh, 44% of the most it could have made running flat out all year (its capacity factor).
How many homes does North English power?
Its 2025 output of 1.3 TWh equals the yearly electricity use of about 128,000 average Iowa homes (861 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is North English?
North English is in Poweshiek County, Iowa, at about 41.643°, -92.499°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Poweshiek County goes 21 hours a year without power, the 2nd most of 98 counties in Iowa. The county's page has the full outage record.
Who operates North English?
It is operated by MidAmerican Energy Co (EIA sector: Electric Utility), and it feeds MISO.
When did North English open?
Its oldest generator still running came online in 2018.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Iowa home's 861 kWh a month in 2025. Methodology.