Solar power plant · Chisago, MN
North Star Solar Project
North Star Solar Project is a 100 MW solar power plant in Chisago County, Minnesota, operated by North Star Solar PV LLC. Its oldest generator still running came online in 2016. In 2025 it generated 181 GWh, about what 20,000 average Minnesota homes use in a year.
North Star Solar Project in context
Among the 544 solar plants in Minnesota in the EIA's inventory, it is the 4th largest, about 4.7% of the state's 2.1 GW of solar capacity.
Chisago County has 43 power plants of 1 MW or more with 191 MW in all; North Star Solar Project is 52% of that and the largest of 42 solar plants there.
Its capacity factor of 21% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Chisago County goes 3.8 hours a year without power, the 17th most of 54 counties in Minnesota. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
North Star Solar Project (outlined) and other plants in Chisago County, shaded. 45.470, -92.910.
Plant facts
- Operator
- North Star Solar PV LLC
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Chisago County, MN
- EIA plant ID
- 59852
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| NSSP1 | Solar Photovoltaic | 100 MW | 2016 | – |
Nearby
Other plants in Chisago County
Questions
North Star Solar Project, answered
How much power does North Star Solar Project produce?
North Star Solar Project has 100 MW of capacity from one generator. In 2025 it generated 181 GWh, 21% of the most it could have made running flat out all year (its capacity factor).
How many homes does North Star Solar Project power?
Its 2025 output of 181 GWh equals the yearly electricity use of about 20,000 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is North Star Solar Project?
North Star Solar Project is in Chisago County, Minnesota, at about 45.470°, -92.910°. It is one of 43 power plants of 1 MW or more in the county. The average electricity customer in Chisago County goes 3.8 hours a year without power, the 17th most of 54 counties in Minnesota. The county's page has the full outage record.
Who operates North Star Solar Project?
It is operated by North Star Solar PV LLC (EIA sector: IPP Non-CHP), and it feeds MISO.
When did North Star Solar Project open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.