Solar power plant · Victoria, TX

Oriana Solar LLC

Oriana Solar LLC is a 180 MW solar power plant in Victoria County, Texas, operated by Oriana Solar LLC. Its oldest generator still running came online in 2025. In 2025 it generated 123 GWh, about what 9,200 average Texas homes use in a year.

Capacity180 MWNameplate, September 2026
Generated123 GWhIn 2025
Capacity factor–Not a full year of data
Generators1Oldest from 2025

Oriana Solar LLC in context

Among the 250 solar plants in Texas in the EIA's inventory, it is the 100th largest, about 0.5% of the state's 37 GW of solar capacity.

Victoria County has 11 power plants of 1 MW or more with 1.2 GW in all; Oriana Solar LLC is 15% of that.

The average electricity customer in Victoria County goes 3.3 hours a year without power, the 221st most of 240 counties in Texas. The county's page has the full outage record.

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Oriana Solar LLC (outlined) and other plants in Victoria County, shaded. 28.905, -96.978.

Plant facts

Operator
Oriana Solar LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Victoria County, TX
EIA plant ID
65849
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ORIPV Solar Photovoltaic 180 MW 2025 –

Questions

Oriana Solar LLC, answered

How much power does Oriana Solar LLC produce?

Oriana Solar LLC has 180 MW of capacity from one generator. In 2025 it generated 123 GWh.

How many homes does Oriana Solar LLC power?

Its 2025 output of 123 GWh equals the yearly electricity use of about 9,200 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Oriana Solar LLC?

Oriana Solar LLC is in Victoria County, Texas, at about 28.905°, -96.978°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Victoria County goes 3.3 hours a year without power, the 221st most of 240 counties in Texas. The county's page has the full outage record.

Who operates Oriana Solar LLC?

It is operated by Oriana Solar LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Oriana Solar LLC open?

Its oldest generator still running came online in 2025.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.