Storage power plant · Hale, TX
Paleo
Paleo is a 200 MW storage power plant in Hale County, Texas, operated by Engie North America. Its oldest generator still running came online in 2024.
Paleo in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 20th largest, about 1.2% of the state's 16 GW of storage capacity.
Hale County has 4 power plants of 1 MW or more with 1.4 GW in all; Paleo is 14% of that.
The average electricity customer in Hale County goes 3.1 hours a year without power, the 223rd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Paleo (outlined) and other plants in Hale County, shaded. 33.889, -101.802.
Plant facts
- Operator
- Engie North America
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Hale County, TX
- EIA plant ID
- 65491
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PALEO | Batteries | 200 MW · 200 MWh | 2024 | – |
Nearby
Other plants in Hale County
Questions
Paleo, answered
How much can Paleo store and deliver?
Paleo can deliver up to 200 MW and hold 200 MWh of energy, from one battery or storage system. Its net energy in 2025 was -16.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Paleo?
Paleo is in Hale County, Texas, at about 33.889°, -101.802°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Hale County goes 3.1 hours a year without power, the 223rd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Paleo?
It is operated by Engie North America (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Paleo open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.