Wind power plant · Glasscock, TX
Panther Creek Wind Farm II
Panther Creek Wind Farm II is a 116 MW wind power plant in Glasscock County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2008. In 2025 it generated 411 GWh, about what 31,000 average Texas homes use in a year.
Panther Creek Wind Farm II in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 180th largest, about 0.3% of the state's 45 GW of wind capacity.
Glasscock County has 6 power plants of 1 MW or more with 743 MW in all; Panther Creek Wind Farm II is 16% of that and the 4th largest of 5 wind plants there.
Its capacity factor of 41% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Glasscock County goes 37 hours a year without power, the 10th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Panther Creek Wind Farm II (outlined) and other plants in Glasscock County, shaded. 31.936, -101.298.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Glasscock County, TX
- EIA plant ID
- 56921
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 116 MW | 2008 | – |
Nearby
Other plants in Glasscock County
Questions
Panther Creek Wind Farm II, answered
How much power does Panther Creek Wind Farm II produce?
Panther Creek Wind Farm II has 116 MW of capacity from one generator. In 2025 it generated 411 GWh, 41% of the most it could have made running flat out all year (its capacity factor).
How many homes does Panther Creek Wind Farm II power?
Its 2025 output of 411 GWh equals the yearly electricity use of about 31,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Panther Creek Wind Farm II?
Panther Creek Wind Farm II is in Glasscock County, Texas, at about 31.936°, -101.298°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Glasscock County goes 37 hours a year without power, the 10th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Panther Creek Wind Farm II?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Panther Creek Wind Farm II open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.