Solar power plant · Goliad, TX
Peregrine Solar
Peregrine Solar is a 300 MW solar power plant in Goliad County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2025. In 2025 it generated 693 GWh, about what 52,000 average Texas homes use in a year.
Peregrine Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 35th largest, about 0.8% of the state's 37 GW of solar capacity.
Goliad County has 2 power plants of 1 MW or more with 922 MW in all; Peregrine Solar is 33% of that.
The average electricity customer in Goliad County goes 20 hours a year without power, the 42nd most of 240 counties in Texas. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Peregrine Solar (outlined) and other plants in Goliad County, shaded. 28.428, -97.454.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Goliad County, TX
- EIA plant ID
- 65979
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PSPV | Solar Photovoltaic | 300 MW | 2025 | – |
Nearby
Other plants in Goliad County
Questions
Peregrine Solar, answered
How much power does Peregrine Solar produce?
Peregrine Solar has 300 MW of capacity from one generator. In 2025 it generated 693 GWh.
How many homes does Peregrine Solar power?
Its 2025 output of 693 GWh equals the yearly electricity use of about 52,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Peregrine Solar?
Peregrine Solar is in Goliad County, Texas, at about 28.428°, -97.454°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Goliad County goes 20 hours a year without power, the 42nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Peregrine Solar?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Peregrine Solar open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.