Natural gas power plant · Tippecanoe, IN
Primient
Primient is a 62 MW natural gas power plant in Tippecanoe County, Indiana, operated by Primary Products Ingredients Americas, LLC d/b/a Primient. Its oldest generator still running came online in 2021. In 2025 it generated 408 GWh, about what 36,000 average Indiana homes use in a year.
Primient in context
Among the 38 natural gas plants in Indiana in the EIA's inventory, it is the 22nd largest, about 0.6% of the state's 10 GW of natural gas capacity.
Tippecanoe County has 7 power plants of 1 MW or more with 138 MW in all; Primient is 45% of that and the largest of 5 natural gas plants there.
Its capacity factor of 75% in 2025 is higher than the 23% typical for natural gas plants across the US.
The average electricity customer in Tippecanoe County goes 3.3 hours a year without power, the 54th most of 90 counties in Indiana. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Primient (outlined) and other plants in Tippecanoe County, shaded. 40.376, -86.844.
Plant facts
- Operator
- Primary Products Ingredients Americas, LLC d/b/a Primient
- Sector
- Industrial CHP
- Grid operator
- MISO
- County
- Tippecanoe County, IN
- EIA plant ID
- 64854
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GTG01 | Natural Gas Fired Combustion Turbine | 31 MW | 2021 | – |
| GTG02 | Natural Gas Fired Combustion Turbine | 31 MW | 2021 | – |
Nearby
Other plants in Tippecanoe County
Questions
Primient, answered
How much power does Primient produce?
Primient has 62 MW of capacity from 2 generators. In 2025 it generated 408 GWh, 75% of the most it could have made running flat out all year (its capacity factor).
How many homes does Primient power?
Its 2025 output of 408 GWh equals the yearly electricity use of about 36,000 average Indiana homes (938 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Primient?
Primient is in Tippecanoe County, Indiana, at about 40.376°, -86.844°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Tippecanoe County goes 3.3 hours a year without power, the 54th most of 90 counties in Indiana. The county's page has the full outage record.
Who operates Primient?
It is operated by Primary Products Ingredients Americas, LLC d/b/a Primient (EIA sector: Industrial CHP), and it feeds MISO.
When did Primient open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Indiana home's 938 kWh a month in 2025. Methodology.