Solar power plant · Madison, TN
Providence Solar
Providence Solar is a 16 MW solar power plant in Madison County, Tennessee, operated by Providence Solar Center, LLC. Its oldest generator still running came online in 2017. In 2025 it generated 31 GWh, about what 2,200 average Tennessee homes use in a year.
Providence Solar in context
Among the 54 solar plants in Tennessee in the EIA's inventory, it is the 11th largest, about 1.3% of the state's 1.2 GW of solar capacity.
Madison County has 3 power plants of 1 MW or more with 87 MW in all; Providence Solar is 18% of that and the 2nd largest of 3 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Madison County goes 3.9 hours a year without power, the 45th most of 73 counties in Tennessee. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Providence Solar (outlined) and other plants in Madison County, shaded. 35.578, -89.048.
Plant facts
- Operator
- Providence Solar Center, LLC
- Sector
- IPP Non-CHP
- Grid operator
- TVA
- County
- Madison County, TN
- EIA plant ID
- 60337
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PROV | Solar Photovoltaic | 16 MW | 2017 | – |
Nearby
Other plants in Madison County
Questions
Providence Solar, answered
How much power does Providence Solar produce?
Providence Solar has 16 MW of capacity from one generator. In 2025 it generated 31 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Providence Solar power?
Its 2025 output of 31 GWh equals the yearly electricity use of about 2,200 average Tennessee homes (1,180 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Providence Solar?
Providence Solar is in Madison County, Tennessee, at about 35.578°, -89.048°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Madison County goes 3.9 hours a year without power, the 45th most of 73 counties in Tennessee. The county's page has the full outage record.
Who operates Providence Solar?
It is operated by Providence Solar Center, LLC (EIA sector: IPP Non-CHP), and it feeds the Tennessee Valley Authority.
When did Providence Solar open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Tennessee home's 1,180 kWh a month in 2025. Methodology.