Storage power plant · Hamilton, TN
Raccoon Mountain
Raccoon Mountain is a 1.7 GW storage power plant in Hamilton County, Tennessee, operated by Tennessee Valley Authority. Its oldest generator still running came online in 1978.
Raccoon Mountain in context
Hamilton County has 5 power plants of 1 MW or more with 4.3 GW in all; Raccoon Mountain is 40% of that.
The average electricity customer in Hamilton County goes 1.8 hours a year without power, the 62nd most of 73 counties in Tennessee. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Raccoon Mountain (outlined) and other plants in Hamilton County, shaded. 35.056, -85.388.
Plant facts
- Operator
- Tennessee Valley Authority
- Sector
- Electric Utility
- Grid operator
- TVA
- County
- Hamilton County, TN
- EIA plant ID
- 6151
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2 | Hydroelectric Pumped Storage | 428 MW | 1978 | – |
| 1 | Hydroelectric Pumped Storage | 428 MW | 1979 | – |
| 3 | Hydroelectric Pumped Storage | 428 MW | 1979 | – |
| 4 | Hydroelectric Pumped Storage | 428 MW | 1979 | – |
Nearby
Other plants in Hamilton County
Questions
Raccoon Mountain, answered
How much can Raccoon Mountain store and deliver?
Raccoon Mountain can deliver up to 1.7 GW, from 4 storage units. Its net energy in 2025 was -537.5 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Raccoon Mountain?
Raccoon Mountain is in Hamilton County, Tennessee, at about 35.056°, -85.388°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Hamilton County goes 1.8 hours a year without power, the 62nd most of 73 counties in Tennessee. The county's page has the full outage record.
Who operates Raccoon Mountain?
It is operated by Tennessee Valley Authority (EIA sector: Electric Utility), and it feeds the Tennessee Valley Authority.
When did Raccoon Mountain open?
Its oldest generator still running came online in 1978.