Solar power plant · Larimer, CO
Rawhide Prairie Solar Hybrid
Rawhide Prairie Solar Hybrid is a 23 MW solar power plant in Larimer County, Colorado, operated by Greenbacker Renewable Energy Corporation. Its oldest generator still running came online in 2021. In 2025 it generated 45 GWh, about what 5,700 average Colorado homes use in a year.
Rawhide Prairie Solar Hybrid in context
Among the 185 solar plants in Colorado in the EIA's inventory, it is the 23rd largest, about 0.6% of the state's 3.8 GW of solar capacity.
Larimer County has 13 power plants of 1 MW or more with 1.1 GW in all; Rawhide Prairie Solar Hybrid is 2% of that and the 2nd largest of 6 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Larimer County goes 1.8 hours a year without power, the 33rd most of 39 counties in Colorado. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Rawhide Prairie Solar Hybrid (outlined) and other plants in Larimer County, shaded. 40.858, -105.016.
Plant facts
- Operator
- Greenbacker Renewable Energy Corporation
- Sector
- IPP Non-CHP
- Grid operator
- PSCO
- County
- Larimer County, CO
- EIA plant ID
- 63722
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 22 MW | 2021 | – |
| BA1 | Batteries | 1.0 MW · 2 MWh | 2021 | – |
Nearby
Other plants in Larimer County
Questions
Rawhide Prairie Solar Hybrid, answered
How much power does Rawhide Prairie Solar Hybrid produce?
Rawhide Prairie Solar Hybrid has 23 MW of capacity from 2 generators. In 2025 it generated 45 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Rawhide Prairie Solar Hybrid power?
Its 2025 output of 45 GWh equals the yearly electricity use of about 5,700 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Rawhide Prairie Solar Hybrid?
Rawhide Prairie Solar Hybrid is in Larimer County, Colorado, at about 40.858°, -105.016°. It is one of 13 power plants of 1 MW or more in the county. The average electricity customer in Larimer County goes 1.8 hours a year without power, the 33rd most of 39 counties in Colorado. The county's page has the full outage record.
Who operates Rawhide Prairie Solar Hybrid?
It is operated by Greenbacker Renewable Energy Corporation (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.
When did Rawhide Prairie Solar Hybrid open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.