Natural gas power plant · Harris, TX

Remy Jade Power Station

Remy Jade Power Station is a 484 MW natural gas power plant in Harris County, Texas, operated by City of San Antonio - (TX). Its oldest generator still running came online in 2024. In 2025 it generated 494 GWh, about what 37,000 average Texas homes use in a year.

Capacity484 MWNameplate, September 2026
Generated494 GWhIn 2025
Capacity factor12%Share of the most it could make, 2025
Generators8Oldest from 2024

Remy Jade Power Station in context

Among the 309 natural gas plants in Texas in the EIA's inventory, it is the 77th largest, about 0.6% of the state's 83 GW of natural gas capacity.

Harris County has 86 power plants of 1 MW or more with 11 GW in all; Remy Jade Power Station is 4% of that and the 8th largest of 66 natural gas plants there.

Its capacity factor of 12% in 2025 is lower than the 23% typical for natural gas plants across the US.

The average electricity customer in Harris County goes 16 hours a year without power, the 66th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060020242025GWh 494
020040060020242025494

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Remy Jade Power Station (outlined) and other plants in Harris County, shaded. 29.848, -95.016.

Plant facts

Operator
City of San Antonio - (TX)
Sector
Electric Utility
Grid operator
ERCO
County
Harris County, TX
EIA plant ID
66604
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CTG-1 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-2 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-3 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-4 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-5 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-6 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-7 Natural Gas Fired Combustion Turbine 61 MW 2024 –
CTG-8 Natural Gas Fired Combustion Turbine 61 MW 2024 –

Questions

Remy Jade Power Station, answered

How much power does Remy Jade Power Station produce?

Remy Jade Power Station has 484 MW of capacity from 8 generators. In 2025 it generated 494 GWh, 12% of the most it could have made running flat out all year (its capacity factor).

How many homes does Remy Jade Power Station power?

Its 2025 output of 494 GWh equals the yearly electricity use of about 37,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Remy Jade Power Station?

Remy Jade Power Station is in Harris County, Texas, at about 29.848°, -95.016°. It is one of 86 power plants of 1 MW or more in the county. The average electricity customer in Harris County goes 16 hours a year without power, the 66th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Remy Jade Power Station?

It is operated by City of San Antonio - (TX) (EIA sector: Electric Utility), and it feeds ERCOT, the Texas grid.

When did Remy Jade Power Station open?

Its oldest generator still running came online in 2024.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.