Storage power plant · Falls, TX
Roseland Solar Project, LLC
Roseland Solar Project, LLC is a 52 MW storage power plant in Falls County, Texas, operated by Enel Green Power Roseland Solar, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 1.0 TWh, about what 78,000 average Texas homes use in a year.
Roseland Solar Project, LLC in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 92nd largest, about 0.3% of the state's 16 GW of storage capacity.
Falls County has 5 power plants of 1 MW or more with 941 MW in all; Roseland Solar Project, LLC is 6% of that.
The average electricity customer in Falls County goes 16 hours a year without power, the 69th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Roseland Solar Project, LLC (outlined) and other plants in Falls County, shaded. 31.461, -96.825.
Plant facts
- Operator
- Enel Green Power Roseland Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Falls County, TX
- EIA plant ID
- 65028
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| ROSEB | Batteries | 52 MW · 85 MWh | 2023 | – |
Planned
| Generator | Technology | Capacity | Expected |
|---|---|---|---|
| ROSES | Solar Photovoltaic | 500 MW | 2026 |
Nearby
Other plants in Falls County
Questions
Roseland Solar Project, LLC, answered
How much can Roseland Solar Project, LLC store and deliver?
Roseland Solar Project, LLC can deliver up to 52 MW and hold 85 MWh of energy, from one battery or storage system. Its net energy in 2025 was 1.0 TWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Roseland Solar Project, LLC?
Roseland Solar Project, LLC is in Falls County, Texas, at about 31.461°, -96.825°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Falls County goes 16 hours a year without power, the 69th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Roseland Solar Project, LLC?
It is operated by Enel Green Power Roseland Solar, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Roseland Solar Project, LLC open?
Its oldest generator still running came online in 2023. 1 more generator is planned.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.