Wind power plant · Elbert, CO

Rush Creek Wind

Rush Creek Wind is a 600 MW wind power plant in Elbert County, Colorado, operated by Public Service Co of Colorado. Its oldest generator still running came online in 2018. In 2025 it generated 2.1 TWh, about what 272,000 average Colorado homes use in a year.

Capacity600 MWNameplate, September 2026
Generated2.1 TWhIn 2025
Capacity factor41%Share of the most it could make, 2025
Generators1Oldest from 2018

Rush Creek Wind in context

Among the 34 wind plants in Colorado in the EIA's inventory, it is the largest, about 10% of the state's 5.9 GW of wind capacity.

Its capacity factor of 41% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Elbert County goes 3.3 hours a year without power, the 18th most of 39 counties in Colorado. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,5002,0002,50020182019202020212022202320242025GWh 2,150
05001,0001,5002,0002,50020192021202320252,150

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Rush Creek Wind (outlined) and other plants in Elbert County, shaded. 39.172, -103.845.

Plant facts

Operator
Public Service Co of Colorado
Sector
Electric Utility
Grid operator
PSCO
County
Elbert County, CO
EIA plant ID
60619
Where Colorado's power comes from → Colorado power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Onshore Wind Turbine 600 MW 2018 –

Questions

Rush Creek Wind, answered

How much power does Rush Creek Wind produce?

Rush Creek Wind has 600 MW of capacity from one generator. In 2025 it generated 2.1 TWh, 41% of the most it could have made running flat out all year (its capacity factor).

How many homes does Rush Creek Wind power?

Its 2025 output of 2.1 TWh equals the yearly electricity use of about 272,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Rush Creek Wind?

Rush Creek Wind is in Elbert County, Colorado, at about 39.172°, -103.845°. The average electricity customer in Elbert County goes 3.3 hours a year without power, the 18th most of 39 counties in Colorado. The county's page has the full outage record.

Who operates Rush Creek Wind?

It is operated by Public Service Co of Colorado (EIA sector: Electric Utility), and it feeds Public Service Company of Colorado.

When did Rush Creek Wind open?

Its oldest generator still running came online in 2018.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.