Solar power plant · Warren, MO
Split Rail Solar Energy LLC
Split Rail Solar Energy LLC is a 300 MW solar power plant in Warren County, Missouri, operated by Union Electric Co - (MO). Its oldest generator still running came online in 2026.
Split Rail Solar Energy LLC in context
Among the 38 solar plants in Missouri in the EIA's inventory, it is the largest, about 16% of the state's 1.9 GW of solar capacity.
Warren County has 2 power plants of 1 MW or more with 439 MW in all; Split Rail Solar Energy LLC is 68% of that and the largest of 2 solar plants there.
The average electricity customer in Warren County goes 7.3 hours a year without power, the 29th most of 110 counties in Missouri. The county's page has the full outage record.
Where it is
Split Rail Solar Energy LLC (outlined) and other plants in Warren County, shaded. 38.901, -91.209.
Plant facts
- Operator
- Union Electric Co - (MO)
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Warren County, MO
- EIA plant ID
- 69475
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SPTRL | Solar Photovoltaic | 300 MW | 2026 | – |
Nearby
Other plants in Warren County
Questions
Split Rail Solar Energy LLC, answered
How much power does Split Rail Solar Energy LLC produce?
Split Rail Solar Energy LLC has 300 MW of capacity from one generator. No full year of generation is reported yet.
Where is Split Rail Solar Energy LLC?
Split Rail Solar Energy LLC is in Warren County, Missouri, at about 38.901°, -91.209°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Warren County goes 7.3 hours a year without power, the 29th most of 110 counties in Missouri. The county's page has the full outage record.
Who operates Split Rail Solar Energy LLC?
It is operated by Union Electric Co - (MO) (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Split Rail Solar Energy LLC open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.