Storey Solar and Storage is a 210 MW solar power plant in Pinal County, Arizona, operated by Storey Energy Center, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 301 GWh, about what 24,000 average Arizona homes use in a year.
Storey Solar and Storage in context
Among the 109 solar plants in Arizona in the EIA's inventory, it is the 12th largest, about 2.1% of the state's 9.9 GW of solar capacity.
Pinal County has 22 power plants of 1 MW or more with 4.9 GW in all; Storey Solar and Storage is 4% of that and the 3rd largest of 14 solar plants there.
Its capacity factor of 16% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Pinal County goes 1.8 hours a year without power, the 5th most of 11 counties in Arizona. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Storey Solar and Storage (outlined) and other plants in Pinal County, shaded. 32.888, -111.498.
Plant facts
- Operator
- Storey Energy Center, LLC
- Sector
- IPP Non-CHP
- Grid operator
- SRP
- County
- Pinal County, AZ
- EIA plant ID
- 65956
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| STORY | Solar Photovoltaic | 122 MW | 2023 | – |
| STOBA | Batteries | 88 MW · 264 MWh | 2023 | – |
Questions
Storey Solar and Storage, answered
How much power does Storey Solar and Storage produce?
Storey Solar and Storage has 210 MW of capacity from 2 generators. In 2025 it generated 301 GWh, 16% of the most it could have made running flat out all year (its capacity factor).
How many homes does Storey Solar and Storage power?
Its 2025 output of 301 GWh equals the yearly electricity use of about 24,000 average Arizona homes (1,030 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Storey Solar and Storage?
Storey Solar and Storage is in Pinal County, Arizona, at about 32.888°, -111.498°. It is one of 22 power plants of 1 MW or more in the county. The average electricity customer in Pinal County goes 1.8 hours a year without power, the 5th most of 11 counties in Arizona. The county's page has the full outage record.
Who operates Storey Solar and Storage?
It is operated by Storey Energy Center, LLC (EIA sector: IPP Non-CHP), and it feeds Salt River Project.
When did Storey Solar and Storage open?
Its oldest generator still running came online in 2023.