Stryker 22, L.L.C. is a 20 MW storage power plant in Warren County, New Jersey, operated by Stryker 22, L.L.C.. Its oldest generator still running came online in 2018.

Capacity20 MWNameplate, September 2026
Net energy-4.9 GWhIn 2025
Capacity factor–Not a full year of data
Generators1Oldest from 2018

Stryker 22, L.L.C. in context

Among the 13 storage plants in New Jersey in the EIA's inventory, it is the 5th largest, about 3.4% of the state's 585 MW of storage capacity.

Warren County has 17 power plants of 1 MW or more with 576 MW in all; Stryker 22, L.L.C. is 3% of that and the 2nd largest of 2 storage plants there.

The average electricity customer in Warren County goes 15 hours a year without power, the 3rd most of 21 counties in New Jersey. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.

00011112019202020212022202320242025GWh -5
00011112019202120232025-5

Where it is

Stryker 22, L.L.C. (outlined) and other plants in Warren County, shaded. 40.665, -75.144.

Plant facts

Operator
Stryker 22, L.L.C.
Sector
IPP Non-CHP
Grid operator
PJM
County
Warren County, NJ
EIA plant ID
61891
Where New Jersey's power comes from → New Jersey power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
EDGRD Batteries 20 MW · 20 MWh 2018 –

Nearby

Other plants in Warren County

Questions

Stryker 22, L.L.C., answered

How much can Stryker 22, L.L.C. store and deliver?

Stryker 22, L.L.C. can deliver up to 20 MW and hold 20 MWh of energy, from one battery or storage system. Its net energy in 2025 was -4.9 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Stryker 22, L.L.C.?

Stryker 22, L.L.C. is in Warren County, New Jersey, at about 40.665°, -75.144°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Warren County goes 15 hours a year without power, the 3rd most of 21 counties in New Jersey. The county's page has the full outage record.

Who operates Stryker 22, L.L.C.?

It is operated by Stryker 22, L.L.C. (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Stryker 22, L.L.C. open?

Its oldest generator still running came online in 2018.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Methodology.