Sweetwater Solar

Sweetwater Solar is a 92 MW solar power plant in Sweetwater County, Wyoming, operated by Onward Energy. Its oldest generator still running came online in 2018. In 2025 it generated 173 GWh, about what 17,000 average Wyoming homes use in a year.

Capacity92 MWNameplate, September 2026
Generated173 GWhIn 2025
Capacity factor22%Share of the most it could make, 2025
Generators1Oldest from 2018

Sweetwater Solar in context

Among the 2 solar plants in Wyoming in the EIA's inventory, it is the 2nd largest, about 38% of the state's 242 MW of solar capacity.

Sweetwater County has 5 power plants of 1 MW or more with 2.5 GW in all; Sweetwater Solar is 4% of that.

Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Sweetwater County goes 2.4 hours a year without power, the 11th most of 20 counties in Wyoming. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020025020182019202020212022202320242025GWh 173
0501001502002502019202120232025173

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Sweetwater Solar (outlined) and other plants in Sweetwater County, shaded. 41.629, -109.683.

Plant facts

Operator
Onward Energy
Sector
IPP Non-CHP
Grid operator
PACE
County
Sweetwater County, WY
EIA plant ID
61369
Where Wyoming's power comes from → Wyoming power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
PV1 Solar Photovoltaic 92 MW 2018 –

Questions

Sweetwater Solar, answered

How much power does Sweetwater Solar produce?

Sweetwater Solar has 92 MW of capacity from one generator. In 2025 it generated 173 GWh, 22% of the most it could have made running flat out all year (its capacity factor).

How many homes does Sweetwater Solar power?

Its 2025 output of 173 GWh equals the yearly electricity use of about 17,000 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Sweetwater Solar?

Sweetwater Solar is in Sweetwater County, Wyoming, at about 41.629°, -109.683°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Sweetwater County goes 2.4 hours a year without power, the 11th most of 20 counties in Wyoming. The county's page has the full outage record.

Who operates Sweetwater Solar?

It is operated by Onward Energy (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Sweetwater Solar open?

Its oldest generator still running came online in 2018.