Storage power plant · Reynolds, MO
Taum Sauk
Taum Sauk is a 408 MW storage power plant in Reynolds County, Missouri, operated by Union Electric Co - (MO). Its oldest generator still running came online in 1963.
Taum Sauk in context
Among the 4 storage plants in Missouri in the EIA's inventory, it is the largest, about 65% of the state's 628 MW of storage capacity.
The average electricity customer in Reynolds County goes 26 hours a year without power, the 1st most of 110 counties in Missouri. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Taum Sauk (outlined) and other plants in Reynolds County, shaded. 37.521, -90.835.
Plant facts
- Operator
- Union Electric Co - (MO)
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Reynolds County, MO
- EIA plant ID
- 2108
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Hydroelectric Pumped Storage | 204 MW | 1963 | – |
| 2 | Hydroelectric Pumped Storage | 204 MW | 1963 | – |
Questions
Taum Sauk, answered
How much can Taum Sauk store and deliver?
Taum Sauk can deliver up to 408 MW, from 2 storage units. Its net energy in 2025 was -159.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Taum Sauk?
Taum Sauk is in Reynolds County, Missouri, at about 37.521°, -90.835°. The average electricity customer in Reynolds County goes 26 hours a year without power, the 1st most of 110 counties in Missouri. The county's page has the full outage record.
Who operates Taum Sauk?
It is operated by Union Electric Co - (MO) (EIA sector: Electric Utility), and it feeds MISO.
When did Taum Sauk open?
Its oldest generator still running came online in 1963.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.