Wind power plant · Hyde, SD
Triple H Wind Project
Triple H Wind Project is a 250 MW wind power plant in Hyde County, South Dakota, operated by Engie North America. Its oldest generator still running came online in 2020. In 2025 it generated 1.0 TWh, about what 87,000 average South Dakota homes use in a year.
Triple H Wind Project in context
Among the 25 wind plants in South Dakota in the EIA's inventory, it is the 3rd largest, about 7.2% of the state's 3.5 GW of wind capacity.
Hyde County has 3 power plants of 1 MW or more with 491 MW in all; Triple H Wind Project is 51% of that and the largest of 3 wind plants there.
Its capacity factor of 47% in 2025 is higher than the 32% typical for wind plants across the US.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Triple H Wind Project (outlined) and other plants in Hyde County, shaded. 44.401, -99.604.
Plant facts
- Operator
- Engie North America
- Sector
- IPP Non-CHP
- Grid operator
- SWPP
- County
- Hyde County, SD
- EIA plant ID
- 63103
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WTG | Onshore Wind Turbine | 250 MW | 2020 | – |
Nearby
Other plants in Hyde County
Questions
Triple H Wind Project, answered
How much power does Triple H Wind Project produce?
Triple H Wind Project has 250 MW of capacity from one generator. In 2025 it generated 1.0 TWh, 47% of the most it could have made running flat out all year (its capacity factor).
How many homes does Triple H Wind Project power?
Its 2025 output of 1.0 TWh equals the yearly electricity use of about 87,000 average South Dakota homes (984 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Triple H Wind Project?
Triple H Wind Project is in Hyde County, South Dakota, at about 44.401°, -99.604°. It is one of 3 power plants of 1 MW or more in the county.
Who operates Triple H Wind Project?
It is operated by Engie North America (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.
When did Triple H Wind Project open?
Its oldest generator still running came online in 2020.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average South Dakota home's 984 kWh a month in 2025. Methodology.