Wind power plant · Twin Falls, ID

Tuana Gulch Wind Park

Tuana Gulch Wind Park is a 11 MW wind power plant in Twin Falls County, Idaho, operated by Idaho Wind Partners 1 LLC. Its oldest generator still running came online in 2011. In 2025 it generated 27 GWh, about what 2,400 average Idaho homes use in a year.

Capacity11 MWNameplate, September 2026
Generated27 GWhIn 2025
Capacity factor30%Share of the most it could make, 2025
Generators1Oldest from 2011

Tuana Gulch Wind Park in context

Among the 33 wind plants in Idaho in the EIA's inventory, it is the 32nd largest, about 0.9% of the state's 1.1 GW of wind capacity.

Twin Falls County has 27 power plants of 1 MW or more with 598 MW in all; Tuana Gulch Wind Park is 2% of that and the 10th largest of 11 wind plants there.

Its capacity factor of 30% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Twin Falls County goes 2.0 hours a year without power, the 31st most of 35 counties in Idaho. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

01020304020182019202020212022202320242025GWh 27
010203040201920212023202527

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Tuana Gulch Wind Park (outlined) and other plants in Twin Falls County, shaded. 42.837, -114.969.

Plant facts

Operator
Idaho Wind Partners 1 LLC
Sector
IPP Non-CHP
Grid operator
IPCO
County
Twin Falls County, ID
EIA plant ID
56443
Where Idaho's power comes from → Idaho power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
TGWP Onshore Wind Turbine 11 MW 2011 –

Questions

Tuana Gulch Wind Park, answered

How much power does Tuana Gulch Wind Park produce?

Tuana Gulch Wind Park has 11 MW of capacity from one generator. In 2025 it generated 27 GWh, 30% of the most it could have made running flat out all year (its capacity factor).

How many homes does Tuana Gulch Wind Park power?

Its 2025 output of 27 GWh equals the yearly electricity use of about 2,400 average Idaho homes (933 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Tuana Gulch Wind Park?

Tuana Gulch Wind Park is in Twin Falls County, Idaho, at about 42.837°, -114.969°. It is one of 27 power plants of 1 MW or more in the county. The average electricity customer in Twin Falls County goes 2.0 hours a year without power, the 31st most of 35 counties in Idaho. The county's page has the full outage record.

Who operates Tuana Gulch Wind Park?

It is operated by Idaho Wind Partners 1 LLC (EIA sector: IPP Non-CHP), and it feeds Idaho Power.

When did Tuana Gulch Wind Park open?

Its oldest generator still running came online in 2011.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Idaho home's 933 kWh a month in 2025. Methodology.