Biomass power plant · Orange, TX
USG Paper, LLC - Orange Mill
USG Paper, LLC - Orange Mill is a 48 MW biomass power plant in Orange County, Texas, operated by USG Paper LLC. Its oldest generator still running came online in 1967.
USG Paper, LLC - Orange Mill in context
Among the 50 other-fuel plants in Texas in the EIA's inventory, it is the 10th largest, about 2.9% of the state's 1.6 GW of other-fuel capacity.
Orange County has 3 power plants of 1 MW or more with 2.5 GW in all; USG Paper, LLC - Orange Mill is 2% of that.
The average electricity customer in Orange County goes 23 hours a year without power, the 34th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Where it is
USG Paper, LLC - Orange Mill (outlined) and other plants in Orange County, shaded. 30.218, -93.742.
Plant facts
- Operator
- USG Paper LLC
- Sector
- Industrial CHP
- Grid operator
- MISO
- County
- Orange County, TX
- EIA plant ID
- 10425
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TG | Wood/Wood Waste Biomass | 48 MW | 1967 | – |
Nearby
Other plants in Orange County
Questions
USG Paper, LLC - Orange Mill, answered
How much power does USG Paper, LLC - Orange Mill produce?
USG Paper, LLC - Orange Mill has 48 MW of capacity from one generator. No full year of generation is reported yet.
Where is USG Paper, LLC - Orange Mill?
USG Paper, LLC - Orange Mill is in Orange County, Texas, at about 30.218°, -93.742°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Orange County goes 23 hours a year without power, the 34th most of 240 counties in Texas. The county's page has the full outage record.
Who operates USG Paper, LLC - Orange Mill?
It is operated by USG Paper LLC (EIA sector: Industrial CHP), and it feeds MISO.
When did USG Paper, LLC - Orange Mill open?
Its oldest generator still running came online in 1967.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.