Natural gas power plant · Benton, IA
Vinton
Vinton is a 18 MW natural gas power plant in Benton County, Iowa, operated by City of Vinton - (IA). Its oldest generator still running came online in 1946.
Vinton in context
Among the 38 natural gas plants in Iowa in the EIA's inventory, it is the 26th largest, about 0.4% of the state's 4.4 GW of natural gas capacity.
The average electricity customer in Benton County goes 13 hours a year without power, the 8th most of 98 counties in Iowa. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Where it is
Vinton (outlined) and other plants in Benton County, shaded. 42.170, -92.022.
Plant facts
- Operator
- City of Vinton - (IA)
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Benton County, IA
- EIA plant ID
- 1194
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 8 | Natural Gas Internal Combustion Engine | 5.6 MW | 1973 | – |
| 7 | Natural Gas Internal Combustion Engine | 3.7 MW | 1967 | – |
| 9 | Natural Gas Internal Combustion Engine | 3.0 MW | 1992 | – |
| 6 | Natural Gas Internal Combustion Engine | 2.5 MW | 1961 | – |
| 1 | Natural Gas Internal Combustion Engine | 1.3 MW | 1955 | – |
| 10 | Petroleum Liquids | 0.8 MW | 2009 | – |
| 5 | Petroleum Liquids | 0.6 MW | 1946 | – |
Questions
Vinton, answered
How much power does Vinton produce?
Vinton has 18 MW of capacity from 7 generators. No full year of generation is reported yet.
Where is Vinton?
Vinton is in Benton County, Iowa, at about 42.170°, -92.022°. The average electricity customer in Benton County goes 13 hours a year without power, the 8th most of 98 counties in Iowa. The county's page has the full outage record.
Who operates Vinton?
It is operated by City of Vinton - (IA) (EIA sector: Electric Utility), and it feeds MISO.
When did Vinton open?
Its oldest generator still running came online in 1946.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.