Biomass power plant · King George, VA
Waste Management King George LFGTE
Waste Management King George LFGTE is a 13 MW biomass power plant in King George County, Virginia, operated by WM Renewable Energy LLC. Its oldest generator still running came online in 2010. In 2025 it generated 78 GWh, about what 6,100 average Virginia homes use in a year.
Waste Management King George LFGTE in context
Among the 55 other-fuel plants in Virginia in the EIA's inventory, it is the 23rd largest, about 0.8% of the state's 1.7 GW of other-fuel capacity.
Its capacity factor of 67% in 2025 is higher than the 25% typical for biomass plants across the US.
The average electricity customer in King George County goes 11 hours a year without power, the 64th most of 123 counties in Virginia. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Waste Management King George LFGTE (outlined) and other plants in King George County, shaded. 38.275, -77.308.
Plant facts
- Operator
- WM Renewable Energy LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- King George County, VA
- EIA plant ID
- 57022
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Landfill Gas | 3.3 MW | 2010 | – |
| GEN2 | Landfill Gas | 3.3 MW | 2010 | – |
| GEN3 | Landfill Gas | 3.3 MW | 2010 | – |
| GEN4 | Landfill Gas | 3.3 MW | 2011 | – |
Questions
Waste Management King George LFGTE, answered
How much power does Waste Management King George LFGTE produce?
Waste Management King George LFGTE has 13 MW of capacity from 4 generators. In 2025 it generated 78 GWh, 67% of the most it could have made running flat out all year (its capacity factor).
How many homes does Waste Management King George LFGTE power?
Its 2025 output of 78 GWh equals the yearly electricity use of about 6,100 average Virginia homes (1,067 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Waste Management King George LFGTE?
Waste Management King George LFGTE is in King George County, Virginia, at about 38.275°, -77.308°. The average electricity customer in King George County goes 11 hours a year without power, the 64th most of 123 counties in Virginia. The county's page has the full outage record.
Who operates Waste Management King George LFGTE?
It is operated by WM Renewable Energy LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Waste Management King George LFGTE open?
Its oldest generator still running came online in 2010.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Virginia home's 1,067 kWh a month in 2025. Methodology.