Solar power plant · Olmsted, MN
Westside Solar
Westside Solar is a 10 MW solar power plant in Olmsted County, Minnesota, operated by Westside Solar, LLC (Ecofin). Its oldest generator still running came online in 2022. In 2025 it generated 19 GWh, about what 2,100 average Minnesota homes use in a year.
Westside Solar in context
Among the 544 solar plants in Minnesota in the EIA's inventory, it is the 15th largest, about 0.5% of the state's 2.1 GW of solar capacity.
Olmsted County has 18 power plants of 1 MW or more with 234 MW in all; Westside Solar is 4% of that and the largest of 10 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Olmsted County goes 1.2 hours a year without power, the 49th most of 54 counties in Minnesota. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Westside Solar (outlined) and other plants in Olmsted County, shaded. 44.054, -92.548.
Plant facts
- Operator
- Westside Solar, LLC (Ecofin)
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Olmsted County, MN
- EIA plant ID
- 66422
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SOUTH | Solar Photovoltaic | 6.5 MW | 2022 | – |
| NORTH | Solar Photovoltaic | 3.5 MW | 2022 | – |
Nearby
Other plants in Olmsted County
Questions
Westside Solar, answered
How much power does Westside Solar produce?
Westside Solar has 10 MW of capacity from 2 generators. In 2025 it generated 19 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Westside Solar power?
Its 2025 output of 19 GWh equals the yearly electricity use of about 2,100 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Westside Solar?
Westside Solar is in Olmsted County, Minnesota, at about 44.054°, -92.548°. It is one of 18 power plants of 1 MW or more in the county. The average electricity customer in Olmsted County goes 1.2 hours a year without power, the 49th most of 54 counties in Minnesota. The county's page has the full outage record.
Who operates Westside Solar?
It is operated by Westside Solar, LLC (Ecofin) (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Westside Solar open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.