Hydro power plant · Thurston, WA

Yelm

Yelm is a 12 MW hydro power plant in Thurston County, Washington, operated by City of Centralia - (WA). Its oldest generator still running came online in 1930. In 2025 it generated 32 GWh, about what 2,800 average Washington homes use in a year.

Capacity12 MWNameplate, September 2026
Generated32 GWhIn 2025
Capacity factor31%Share of the most it could make, 2025
Generators3Oldest from 1930

Yelm in context

Among the 73 hydro plants in Washington in the EIA's inventory, it is the 49th largest, about 0.1% of the state's 22 GW of hydro capacity.

Thurston County has 3 power plants of 1 MW or more with 149 MW in all; Yelm is 8% of that and the largest of 2 hydro plants there.

Its capacity factor of 31% in 2025 is close to the 34% typical for hydro plants across the US.

The average electricity customer in Thurston County goes 6.4 hours a year without power, the 15th most of 31 counties in Washington. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02040608010020182019202020212022202320242025GWh 32
020406080100201920212023202532

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Yelm (outlined) and other plants in Thurston County, shaded. 46.975, -122.636.

Plant facts

Operator
City of Centralia - (WA)
Sector
Electric Utility
Grid operator
BPAT
County
Thurston County, WA
EIA plant ID
3878
Where Washington's power comes from → Washington power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
3 Conventional Hydroelectric 6.0 MW 1955 –
1 Conventional Hydroelectric 3.0 MW 1930 –
2 Conventional Hydroelectric 3.0 MW 1930 –

Nearby

Other plants in Thurston County

Skookumchuck Wind Facility · 136 MWSkookumchuck · 1.0 MW

Questions

Yelm, answered

How much power does Yelm produce?

Yelm has 12 MW of capacity from 3 generators. In 2025 it generated 32 GWh, 31% of the most it could have made running flat out all year (its capacity factor).

How many homes does Yelm power?

Its 2025 output of 32 GWh equals the yearly electricity use of about 2,800 average Washington homes (945 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Yelm?

Yelm is in Thurston County, Washington, at about 46.975°, -122.636°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Thurston County goes 6.4 hours a year without power, the 15th most of 31 counties in Washington. The county's page has the full outage record.

Who operates Yelm?

It is operated by City of Centralia - (WA) (EIA sector: Electric Utility), and it feeds the Bonneville Power Administration.

When did Yelm open?

Its oldest generator still running came online in 1930.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Washington home's 945 kWh a month in 2025. Methodology.