Rooftop solar · 2025
Maryland
118,789 homes in Maryland had rooftop solar connected to the grid at the end of 2025: 4.8% of residential customers, 1.3× the US share of 3.8%. That ranks 12th of 51.
Growth
Solar installations, year by year
Net-metered solar installations at the end of each year, all customers and homes only. Maryland went from 66,105 in 2018 to 121,117 in 2025.
Capacity
Megawatts on rooftops
Net-metered solar capacity in MW. Utilities report it in AC or DC; EIA adds the two together.
Backup power
Batteries that keep the lights on
Net-metered batteries. Those paired with solar can keep a home running through an outage. Batteries without solar are reported separately from 2023.
Maryland among the states
- Share of homes with solar4.8%12th
- Solar installations121,11712th
- Net-metered capacity1.3 GW9th
- Growth in installations since 20181.8×44th
- Batteries per 10,000 homes3.123rd
Utility by utility
Solar on each utility's lines
Net-metered solar reported by each Maryland utility for 2025. Share of homes is residential installations over residential customers.
| Utility | Installations | Capacity | Share of homes | With battery |
|---|---|---|---|---|
| Baltimore Gas & Electric Co | 53,215 | 521 MW | 4.3% | – |
| Potomac Electric Power Co | 40,241 | 408 MW | 7.1% | – |
| Southern Maryland Elec Coop Inc | 9,590 | 94 MW | 5.8% | 368 |
| The Potomac Edison Company | 8,975 | 141 MW | 3.4% | 387 |
| Delmarva Power | 7,487 | 104 MW | 3.8% | – |
| Choptank Electric Cooperative, Inc | 1,490 | 23 MW | 2.8% | – |
| Easton Utilities Comm | 77 | 3.9 MW | 0.6% | – |
| Hagerstown Light Department | 42 | 0.5 MW | 0.3% | – |
Beyond net metering
Other generators on customers' sites
Generators of under 1 MW that Maryland utilities know about but do not net-meter, 2025.
Source: U.S. Energy Information Administration, Form EIA-861, net metering and non-net-metered distributed generation files, 2018–2025. State totals include EIA's estimates for small utilities that file the short form. Installations were counted as customers before 2021. How these numbers are built.