Storage power plant · Cobb, GA
Allatoona Substation #10
Allatoona Substation #10 is a 10 MW storage power plant in Cobb County, Georgia, operated by Cobb Electric Membership Corporation. Its oldest generator still running came online in 2026.
Allatoona Substation #10 in context
Among the 6 storage plants in Georgia in the EIA's inventory, it is the 6th largest, about 0.4% of the state's 2.4 GW of storage capacity.
Cobb County has 4 power plants of 1 MW or more with 2.9 GW in all; Allatoona Substation #10 is 0% of that.
The average electricity customer in Cobb County goes 2.2 hours a year without power, the 145th most of 156 counties in Georgia. The county's page has the full outage record.
Where it is
Allatoona Substation #10 (outlined) and other plants in Cobb County, shaded. 34.087, -84.719.
Plant facts
- Operator
- Cobb Electric Membership Corporation
- Sector
- Electric Utility
- Grid operator
- SOCO
- County
- Cobb County, GA
- EIA plant ID
- 69688
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BES02 | Batteries | 10 MW · 40 MWh | 2026 | – |
Nearby
Other plants in Cobb County
Questions
Allatoona Substation #10, answered
How much can Allatoona Substation #10 store and deliver?
Allatoona Substation #10 can deliver up to 10 MW and hold 40 MWh of energy, from one battery or storage system.
Where is Allatoona Substation #10?
Allatoona Substation #10 is in Cobb County, Georgia, at about 34.087°, -84.719°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Cobb County goes 2.2 hours a year without power, the 145th most of 156 counties in Georgia. The county's page has the full outage record.
Who operates Allatoona Substation #10?
It is operated by Cobb Electric Membership Corporation (EIA sector: Electric Utility), and it feeds Southern Company.
When did Allatoona Substation #10 open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.