Wind power plant · Kinney, TX
Anacacho Wind Farm, LLC
Anacacho Wind Farm, LLC is a 100 MW wind power plant in Kinney County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2012. In 2025 it generated 324 GWh, about what 24,000 average Texas homes use in a year.
Anacacho Wind Farm, LLC in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 189th largest, about 0.2% of the state's 45 GW of wind capacity.
Kinney County has 3 power plants of 1 MW or more with 340 MW in all; Anacacho Wind Farm, LLC is 29% of that.
Its capacity factor of 37% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Kinney County goes 27 hours a year without power, the 20th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Anacacho Wind Farm, LLC (outlined) and other plants in Kinney County, shaded. 29.235, -100.209.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Kinney County, TX
- EIA plant ID
- 58000
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| ANA | Onshore Wind Turbine | 100 MW | 2012 | – |
Nearby
Other plants in Kinney County
Questions
Anacacho Wind Farm, LLC, answered
How much power does Anacacho Wind Farm, LLC produce?
Anacacho Wind Farm, LLC has 100 MW of capacity from one generator. In 2025 it generated 324 GWh, 37% of the most it could have made running flat out all year (its capacity factor).
How many homes does Anacacho Wind Farm, LLC power?
Its 2025 output of 324 GWh equals the yearly electricity use of about 24,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Anacacho Wind Farm, LLC?
Anacacho Wind Farm, LLC is in Kinney County, Texas, at about 29.235°, -100.209°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Kinney County goes 27 hours a year without power, the 20th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Anacacho Wind Farm, LLC?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Anacacho Wind Farm, LLC open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.