Solar power plant · Kinney, TX
OCI Alamo 4, LLC
OCI Alamo 4, LLC is a 40 MW solar power plant in Kinney County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2014. In 2025 it generated 71 GWh, about what 5,300 average Texas homes use in a year.
OCI Alamo 4, LLC in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 169th largest, about 0.1% of the state's 37 GW of solar capacity.
Kinney County has 3 power plants of 1 MW or more with 340 MW in all; OCI Alamo 4, LLC is 12% of that and the 2nd largest of 2 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Kinney County goes 27 hours a year without power, the 20th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
OCI Alamo 4, LLC (outlined) and other plants in Kinney County, shaded. 29.330, -100.390.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Kinney County, TX
- EIA plant ID
- 58717
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 40 MW | 2014 | – |
Nearby
Other plants in Kinney County
Questions
OCI Alamo 4, LLC, answered
How much power does OCI Alamo 4, LLC produce?
OCI Alamo 4, LLC has 40 MW of capacity from one generator. In 2025 it generated 71 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does OCI Alamo 4, LLC power?
Its 2025 output of 71 GWh equals the yearly electricity use of about 5,300 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is OCI Alamo 4, LLC?
OCI Alamo 4, LLC is in Kinney County, Texas, at about 29.330°, -100.390°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Kinney County goes 27 hours a year without power, the 20th most of 240 counties in Texas. The county's page has the full outage record.
Who operates OCI Alamo 4, LLC?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did OCI Alamo 4, LLC open?
Its oldest generator still running came online in 2014.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.