Storage power plant · Cochise, AZ

Apache Solar I

Apache Solar I is a 40 MW storage power plant in Cochise County, Arizona, operated by Arizona Electric Pwr Coop Inc. Its oldest generator still running came online in 2017. In 2025 it generated 55 GWh, about what 4,500 average Arizona homes use in a year.

Capacity40 MWNameplate, September 2026
Net energy55 GWhIn 2025
Capacity factor–Not a full year of data
Generators3Oldest from 2017

Apache Solar I in context

Among the 41 storage plants in Arizona in the EIA's inventory, it is the 31st largest, about 0.6% of the state's 6.3 GW of storage capacity.

Cochise County has 10 power plants of 1 MW or more with 1.7 GW in all; Apache Solar I is 2% of that and the 2nd largest of 3 storage plants there.

The average electricity customer in Cochise County goes 0.6 hours a year without power, the 11th most of 11 counties in Arizona. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.

02040608020182019202020212022202320242025GWh 55
020406080201920212023202555

Where it is

Apache Solar I (outlined) and other plants in Cochise County, shaded. 32.068, -109.890.

Plant facts

Operator
Arizona Electric Pwr Coop Inc
Sector
Electric Utility
Grid operator
WALC
County
Cochise County, AZ
EIA plant ID
60964
  • Solar20 MW50%
  • Storage20 MW50%
Where Arizona's power comes from → Arizona power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
AEPS1 Solar Photovoltaic 20 MW 2017 –
AEPB1 Batteries 10 MW · 40 MWh 2024 –
TRIB1 Batteries 10 MW · 40 MWh 2024 –

Questions

Apache Solar I, answered

How much can Apache Solar I store and deliver?

Apache Solar I can deliver up to 40 MW and hold 80 MWh of energy, from 3 storage units. Its net energy in 2025 was 55 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Apache Solar I?

Apache Solar I is in Cochise County, Arizona, at about 32.068°, -109.890°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Cochise County goes 0.6 hours a year without power, the 11th most of 11 counties in Arizona. The county's page has the full outage record.

Who operates Apache Solar I?

It is operated by Arizona Electric Pwr Coop Inc (EIA sector: Electric Utility), and it feeds balancing authority WALC.

When did Apache Solar I open?

Its oldest generator still running came online in 2017.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.