Red Horse 2 is a 81 MW solar power plant in Cochise County, Arizona, operated by Red Horse 2. Its oldest generator still running came online in 2015. In 2025 it generated 144 GWh, about what 12,000 average Arizona homes use in a year.

Capacity81 MWNameplate, September 2026
Generated144 GWhIn 2025
Capacity factor20%Share of the most it could make, 2025
Generators2Oldest from 2015

Red Horse 2 in context

Among the 109 solar plants in Arizona in the EIA's inventory, it is the 36th largest, about 0.8% of the state's 9.9 GW of solar capacity.

Cochise County has 10 power plants of 1 MW or more with 1.7 GW in all; Red Horse 2 is 5% of that and the 2nd largest of 5 solar plants there.

Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Cochise County goes 0.6 hours a year without power, the 11th most of 11 counties in Arizona. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020025020182019202020212022202320242025GWh 144
0501001502002502019202120232025144

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Red Horse 2 (outlined) and other plants in Cochise County, shaded. 32.286, -110.088.

Plant facts

Operator
Red Horse 2
Sector
IPP Non-CHP
Grid operator
TEPC
County
Cochise County, AZ
EIA plant ID
58833
  • Solar51 MW63%
  • Wind30 MW37%
Where Arizona's power comes from → Arizona power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
RH2S Solar Photovoltaic 51 MW 2015 –
RH2W Onshore Wind Turbine 30 MW 2015 –

Questions

Red Horse 2, answered

How much power does Red Horse 2 produce?

Red Horse 2 has 81 MW of capacity from 2 generators. In 2025 it generated 144 GWh, 20% of the most it could have made running flat out all year (its capacity factor).

How many homes does Red Horse 2 power?

Its 2025 output of 144 GWh equals the yearly electricity use of about 12,000 average Arizona homes (1,030 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Red Horse 2?

Red Horse 2 is in Cochise County, Arizona, at about 32.286°, -110.088°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Cochise County goes 0.6 hours a year without power, the 11th most of 11 counties in Arizona. The county's page has the full outage record.

Who operates Red Horse 2?

It is operated by Red Horse 2 (EIA sector: IPP Non-CHP), and it feeds balancing authority TEPC.

When did Red Horse 2 open?

Its oldest generator still running came online in 2015.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.