Apple Data Center PV3 is a 18 MW solar power plant in Catawba County, North Carolina, operated by Apple, Inc. Its oldest generator still running came online in 2015. In 2025 it generated 33 GWh, about what 2,700 average North Carolina homes use in a year.

Capacity18 MWNameplate, September 2026
Generated33 GWhIn 2025
Capacity factor22%Share of the most it could make, 2025
Generators1Oldest from 2015

Apple Data Center PV3 in context

Among the 756 solar plants in North Carolina in the EIA's inventory, it is the 79th largest, about 0.2% of the state's 7.1 GW of solar capacity.

Catawba County has 16 power plants of 1 MW or more with 2.3 GW in all; Apple Data Center PV3 is 1% of that and the 4th largest of 13 solar plants there.

Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Catawba County goes 7.1 hours a year without power, the 60th most of 100 counties in North Carolina. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

01020304020182019202020212022202320242025GWh 33
010203040201920212023202533

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Apple Data Center PV3 (outlined) and other plants in Catawba County, shaded. 35.715, -81.150.

Plant facts

Operator
Apple, Inc
Sector
Commercial Non-CHP
Grid operator
DUK
County
Catawba County, NC
EIA plant ID
59474
Where North Carolina's power comes from → North Carolina power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
DCPV3 Solar Photovoltaic 18 MW 2015 –

Nearby

Other plants in Catawba County

Questions

Apple Data Center PV3, answered

How much power does Apple Data Center PV3 produce?

Apple Data Center PV3 has 18 MW of capacity from one generator. In 2025 it generated 33 GWh, 22% of the most it could have made running flat out all year (its capacity factor).

How many homes does Apple Data Center PV3 power?

Its 2025 output of 33 GWh equals the yearly electricity use of about 2,700 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Apple Data Center PV3?

Apple Data Center PV3 is in Catawba County, North Carolina, at about 35.715°, -81.150°. It is one of 16 power plants of 1 MW or more in the county. The average electricity customer in Catawba County goes 7.1 hours a year without power, the 60th most of 100 counties in North Carolina. The county's page has the full outage record.

Who operates Apple Data Center PV3?

It is operated by Apple, Inc (EIA sector: Commercial Non-CHP), and it feeds Duke Energy Carolinas.

When did Apple Data Center PV3 open?

Its oldest generator still running came online in 2015.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.