Natural gas power plant · Butler, KS

Augusta Electric Plant No 1

Augusta Electric Plant No 1 is a 12 MW natural gas power plant in Butler County, Kansas, operated by City of Augusta - (KS). Its oldest generator still running came online in 1929.

Capacity12 MWNameplate, September 2026
Generated–Not reported
Capacity factor–Not a full year of data
Generators8Oldest from 1929

Augusta Electric Plant No 1 in context

Among the 54 natural gas plants in Kansas in the EIA's inventory, it is the 39th largest, about 0.3% of the state's 4.2 GW of natural gas capacity.

Butler County has 6 power plants of 1 MW or more with 223 MW in all; Augusta Electric Plant No 1 is 5% of that and the 3rd largest of 3 natural gas plants there.

The average electricity customer in Butler County goes 2.2 hours a year without power, the 62nd most of 81 counties in Kansas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

000111120182019202020222023GWh -0
000111120182019202020222023-0

Where it is

Augusta Electric Plant No 1 (outlined) and other plants in Butler County, shaded. 37.678, -96.972.

Plant facts

Operator
City of Augusta - (KS)
Sector
Electric Utility
Grid operator
SWPP
County
Butler County, KS
EIA plant ID
1261
  • Natural gas8.5 MW74%
  • Other3.0 MW26%
Where Kansas's power comes from → Kansas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
5 Natural Gas Internal Combustion Engine 2.2 MW 1956 –
6 Natural Gas Internal Combustion Engine 2.2 MW 1956 –
7 Natural Gas Internal Combustion Engine 2.0 MW 1964 –
8 Petroleum Liquids 2.0 MW 2016 –
1 Natural Gas Internal Combustion Engine 1.1 MW 1954 –
3 Natural Gas Internal Combustion Engine 1.0 MW 1949 –
4 Petroleum Liquids 0.7 MW 1939 –
2 Petroleum Liquids 0.3 MW 1929 –

Nearby

Other plants in Butler County

Elk River Wind · 150 MWEl Dorado Refinery · 39 MWAugusta Electric Plant No 2 · 21 MWPrairie Sky Solar Farm · 1.0 MWDeGraff Butler Electric · 1.0 MW

Questions

Augusta Electric Plant No 1, answered

How much power does Augusta Electric Plant No 1 produce?

Augusta Electric Plant No 1 has 12 MW of capacity from 8 generators. No full year of generation is reported yet.

Where is Augusta Electric Plant No 1?

Augusta Electric Plant No 1 is in Butler County, Kansas, at about 37.678°, -96.972°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Butler County goes 2.2 hours a year without power, the 62nd most of 81 counties in Kansas. The county's page has the full outage record.

Who operates Augusta Electric Plant No 1?

It is operated by City of Augusta - (KS) (EIA sector: Electric Utility), and it feeds the Southwest Power Pool.

When did Augusta Electric Plant No 1 open?

Its oldest generator still running came online in 1929.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.